FOUR LAKES TASK FORCE
  • About
    • History
    • Who We Are >
      • Team Bios
    • Operations
    • Secord Dam
    • Smallwood Dam
    • Edenville Dam
    • Sanford Dam
  • Restoration Progress Report
  • Donate
    • Why Donate?
    • Our Donors >
      • Corporate Sponsors
      • Individual Donors
    • Four Lakes Legacy Society
  • Events
  • Documents
    • Annual & Quarterly Reports
    • Audited Financials
    • Dam Construction Updates
    • Engineering Reports & Studies
    • Flyers & Brochures
    • Meeting Presentations
    • News Flashes & Newsletters
    • Published Statements
    • Restoration Plan 2021
    • Tax Filings & Governance
  • Resources
    • Erosion Control >
      • Project Map
      • Project Permitting
      • What You Can Do
    • FOIA Request
    • Frequently Asked Questions
    • Lakebottom Information
    • Subscribe
    • Updates
  • Special Assessment District
    • Assessment Maps
    • FAQs
    • Prepayments
  • Contact

UPDATES

Dam Restoration Suspension Timeline

3/4/2024

 
An updated suspension schedule was posted May 17, 2024. Please view it here.

Today Four Lakes Task Force (FLTF), the Delegated Authority for restoring the four lakes and dams in Midland and Gladwin counties, announced the Schedule for suspending restoration construction work in the coming months on Secord, Smallwood, Edenville and Sanford dams, and that the start of Edenville Dam’s final phase of construction will be delayed. 
PictureWork will suspend on Secord Dam in June 2024 shortly after the completion of the auxiliary spillway (pictured).
On February 21, 2024, Heron Cove Association (HCA) filed a claim of appeal in Midland Circuit Court requesting that the lake level special assessments be set aside. The process for appeal could take several months. FLTF is not able to issue bonds in June as planned to finance the completion of the Four Lakes dam reconstruction final project phases. Additional unnecessary costs are now accruing that will impact the community with an uncertain outcome.

“This appeal has impacted FLTF’s plan to acquire financing in June, and it is uncertain when or if we can issue bonds required to proceed with the construction to complete the project,” said Dave Kepler, president and chairperson of Four Lakes Task Force. “While we respect peoples’ right to appeal, it is a setback and disappointing considering the progress we have made as a community to restore our lakes. The appeal puts us in a position where we are limited to use only State of Michigan grant funds and must ration the work that can take place.”

With uncertainty regarding funding for the lakes’ restoration, no dam can be fully restored unless this issue of the appeal is resolved. Certain items of the project now underway must be completed on each of the dams with the remaining approximately $100 million of available State of Michigan funds to ensure dam safety requirements are met.

The Edenville embankment upgrades, auxiliary spillways on Secord and Smallwood, and certain phases of construction on the east side of the Sanford Dam will be finished. The Edenville restoration construction final phase, currently awaiting a final permit, will not start as planned. The restoration projects on the other dams will be halted once the current phase of work is completed.

“We hope to have clarity before September on funding for the capital improvements and operations and maintenance of the dams,” Kepler said. “With that, we can move forward. Without it, we are on hold for the foreseeable future on if and when the lakes will be restored.”

Four Lakes’ Dams Anticipated Work Suspension Schedule

Dam
Suspension Date and Description
Secord
June 2024
Shortly after the completion of the auxiliary spillway
Smallwood
​August 2024
After auxiliary spillway is complete and the low flow outlet is stabilized
Edenville
May 2024
The final phase of the Edenville Dam, planned to start by May (pending permit), is now delayed until financing
September 2024
The completion of the current embankment improvement project
Sanford
​December 2024
Completion of the current east side work
The Four Lakes restoration project is operated and financed as one project in phases. This Schedule assumes an inability to proceed with financing before September 2024 for the final phases of the lakes’ restoration. With this schedule, $162 million of the $180 million of state funding being applied to the dams’ restoration will be spent by the end of 2024, assuming FLTF is unable to obtain financing before September 2024. Anticipated expenditures by dam by the end of 2024 using State of Michigan funds for this schedule will be:
  • Secord                              $53 million
  • Smallwood                       $35 million
  • Edenville                          $30 million
  • Sanford                            $39 million
  • All Dams                          $5 million (work not tracked to a specific dam, applies to all four)

The remaining $18 million is reserved for contingency to carry out the suspension work, as well as to ensure there are maintenance funds going into 2025 and 2026. The FLTF dam safety engineers have been engaged in determining the safest pause points given the resource constraints. The Michigan Department of Environment, Great Lakes, and Energy has been notified and discussions are in place to finalize these plans.

Note: A three-month delay to the project will have a cost increase impact of $1.5-$3 million. This increase assumes certainty on financing before September 2024. Should the pause extend further, the cost increase will be greater.

Comments are closed.

    ​UPDATES SENT TO YOUR INBOX

    Fill out this form to subscribe to receive news and updates. 
    Please select why you're interested in receiving updates.

    Thank you!

    You have successfully joined our subscriber list.

    .

    Categories

    All
    Bottomland
    Dams
    Debris Removal
    Drawdown
    Erosion
    Flood 2020
    Funding
    Hydropower
    Legislation
    Meeting
    Part 307/Lake Levels
    Public Hearing/Meeting Notice
    Restoration/Recovery
    Special Assessment District
    Update

    Archives

    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    September 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    December 2022
    November 2022
    October 2022
    September 2022
    August 2022
    July 2022
    June 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    May 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    October 2020
    September 2020
    August 2020
    July 2020
    June 2020
    May 2020
    April 2020
    January 2020
    December 2019
    October 2019
    September 2019
    June 2019
    May 2019
    April 2019
    March 2019

About Us
Meet the board
Read our history
See our supporters
Learn More
Frequently asked questions
Special Assessment District
View documents
See updates
Get Involved
Donate
Attend a meeting
Contact us
Subscribe for email updates

Ask a question • Get our emails
©2025 | Four Lakes Task Force is a US 501 (c)(3) public charity, EIN 27-4698447. This institution is an equal opportunity provider.
Four Lakes Task Force
  • About
    • History
    • Who We Are >
      • Team Bios
    • Operations
    • Secord Dam
    • Smallwood Dam
    • Edenville Dam
    • Sanford Dam
  • Restoration Progress Report
  • Donate
    • Why Donate?
    • Our Donors >
      • Corporate Sponsors
      • Individual Donors
    • Four Lakes Legacy Society
  • Events
  • Documents
    • Annual & Quarterly Reports
    • Audited Financials
    • Dam Construction Updates
    • Engineering Reports & Studies
    • Flyers & Brochures
    • Meeting Presentations
    • News Flashes & Newsletters
    • Published Statements
    • Restoration Plan 2021
    • Tax Filings & Governance
  • Resources
    • Erosion Control >
      • Project Map
      • Project Permitting
      • What You Can Do
    • FOIA Request
    • Frequently Asked Questions
    • Lakebottom Information
    • Subscribe
    • Updates
  • Special Assessment District
    • Assessment Maps
    • FAQs
    • Prepayments
  • Contact