FOUR LAKES TASK FORCE
  • About
    • History
    • Who We Are >
      • Team Bios
    • Operations
    • Secord Dam
    • Smallwood Dam
    • Edenville Dam
    • Sanford Dam
  • Restoration Progress
    • 2025 Restoration Report
    • 2024 Restoration Progress Report
  • Environmental Restoration
    • Lakebottom Information
    • Restoration Projects
    • Erosion Control >
      • Project Permitting
      • What You Can Do
  • Donate
    • Why Donate?
    • Our Donors >
      • Corporate Sponsors
      • Individual Donors
    • Four Lakes Legacy Society
  • Events
  • Documents
    • Annual & Quarterly Reports
    • Audited Financials & Tax Filings
    • Dam Construction Updates
    • Engineering Reports & Studies
    • Flyers & Brochures
    • Meeting Presentations
    • News Flashes & Newsletters
  • Resources
    • FOIA Request
    • Frequently Asked Questions
    • Subscribe
    • Updates
  • Special Assessment District
    • Assessment Maps
    • FAQs
    • Prepayments
  • Contact

Document Library

Click on links in the sidebar to see documents in that category.

2024 four-year progress report

5/20/2024

 

The four lakes four years after edenville failure

​This month marks four years since the failures of Edenville and Sanford dams and the FERC orders to lower Secord and Smallwood lakes. Construction is underway on every dam utilizing funds from a State of Michigan grant. In addition, Four Lakes Task Force (FLTF) and the Gladwin and Midland County Boards of Commissioners approved the computation of costs and assessment rolls to finance the final phases of construction. These were substantial milestones this year.
However, an administrative appeal brought uncertainty to the timing of completion. FLTF has responded and last week communicated revised plans on how construction will continue but would be suspended at a point where each dam is stable and safe unless and until we are able to secure municipal (bond) financing by September. FLTF has followed the law, been transparent, and respected that property owners have the right to appeal. This report provides a status of the project four years after the failures.

While we are working towards a positive resolution to the special assessment appeal, we remain engaged with the Michigan Department of Environment, Great Lakes, and Energy (EGLE) to obtain the final Edenville dam construction permit, and a permit related to the endangered Snuffbox mussel from the U.S. Fish and Wildlife Service based on the Habitat Control Plan.

Walking away is not an option and we do not plan to. The lakes cannot exist without restoration of the dams, and we cannot proceed without the support of the Four Lakes Special Assessment District. Likewise, the dams cannot remain in the watershed without a commitment to restore them. The path to remove the dams would result in a significant new effort to stabilize and restore a different environment, with uncertainties of investment, and no current knowledge of any private or government entity that could or would desire to administer, finance or maintain this option.

Restoration of the lakes is the best environmental and economical path forward, preserving and protecting property values, and improving the quality of life in our communities.

We extend our thanks to the hundreds of talented individuals who work on this project, all our volunteers, and the thousands of people over the last four years who have supported the restoration of the Four Lakes.

President, Four Lakes Task Force
Dave Kepler
​
On behalf of the Four Lakes Board of Directors

Construction Status

Some wonder if we are "over-building the dams.” All the dams suffered from inadequate capacity (which required auxiliary spillways to pass larger flood flows), deteriorating concrete, gates beyond their design life, and unstable embankments. The auxiliary spillways are designed to protect the dams from failure, not control flooding. The dams are designed to manage court-ordered lake levels, and be safe in those operations, including withstanding water flow in storms much larger than the 2020 storm. Since work began on the dams, crews have logged a total of 231,556.55 hours of work* on the sites. Please take time to read our May Construction Newsletter, issued last week, for more information.
*As of April 25, 2024

Cost and Schedule

The Four Lakes restoration project is operated and financed as one project undertaken in phases. Adjustments in the construction schedule were made to accommodate the uncertainty of municipal financing required to complete the project. If the administrative appeal and litigation in connection with the lake level special assessment rolls is not resolved by September and we are unable to sell municipal bonds, there will be an approximately $3 to 5 million impact to project costs. Meaning, delays will increase project costs considerably. Any savings realized by issuing tax-exempt municipal bonds, will be lost.

​If we are delayed anytime between October 2024 - April 2025, and are not able to issue municipal bonds, the project cost would be impacted by increases of $10.6 - $19.7 million. The project can be restarted for the summer construction season in April 2025, but the estimated substantial completion dates will have to be re-estimated. The project computation of cost would not change, as this increase could be managed within the project contingency. However, it makes it more challenging to reduce the total amount to be assessed. At this time, there is too much uncertainty to estimate completion dates if the project starts beyond April, but there would be significant project cost increases and delays in restoration if the 2025 summer construction season is lost.

We are working hard to find certainty by September 2024. The estimated schedules are listed below.
 
Suspension Schedule if Financing is Not Resolved by September 2024
 
The tables below show the timing and construction status for each dam when construction is suspended if we are not able to have our financing in place by September 2024. Each dam will be left in a stable state that can be managed by FLTF Operations.
Dam
Suspension Date and Description
Secord
September 2024
​Shortly after the completion of the auxiliary spillway
Smallwood
September 2024
After auxiliary spillway is complete and the low flow outlet is stabilized
Edenville
September 2024
After completion of the current embankment improvement project
DELAYED
The final phase of the Edenville Dam is now delayed until financing
Sanford
December 2024
​After completion of the current work near primary spillway
Current Estimate of Substantial Completion Dates

Below are the estimated dates of when each dam will be substantially complete if we are able to secure municipal financing by September. Otherwise, the projects will remain suspended until we can secure financing.
Lake
Previously Published Oct. 2023 
​Estimated Substantial Completion Date
Current Estimated Substantial Completion Date
Secord
September 2025
​+/-3 months
November 2025
​+/-3 months
Smallwood
March 2025
​+/-3 months
​​May 2025
​+/-3 months
Wixom
August 2026
​+/-6 months
August 2027
​+/-6 months
Sanford
​April 2026
​+8/-3 months
May 2026
​+/-3 months

Comments are closed.

    Categories

    All
    2018 2019
    2018-2019
    2020
    2021
    2022
    2023
    2024
    2025
    Annual Reports & Quarterly Updates
    Assessment Appeal 2024
    Audited Financials & Tax Filings
    County Documents
    Dam Construction Updates
    Edenville/Wixom
    Engineering Reports & Studies
    Flyers & Brochures
    Governance
    Mailings
    Meetings
    News Flashes & Newsletters
    Publications & Partner Presentations
    Resources And Statements
    Sanford
    Secord
    Smallwood

    Archives

    November 2025
    October 2025
    September 2025
    August 2025
    July 2025
    June 2025
    May 2025
    April 2025
    March 2025
    February 2025
    January 2025
    December 2024
    November 2024
    October 2024
    September 2024
    August 2024
    July 2024
    June 2024
    May 2024
    April 2024
    March 2024
    February 2024
    January 2024
    December 2023
    November 2023
    October 2023
    August 2023
    July 2023
    June 2023
    May 2023
    April 2023
    March 2023
    February 2023
    January 2023
    December 2022
    November 2022
    October 2022
    July 2022
    May 2022
    April 2022
    March 2022
    February 2022
    January 2022
    December 2021
    November 2021
    October 2021
    September 2021
    August 2021
    July 2021
    June 2021
    April 2021
    March 2021
    February 2021
    January 2021
    December 2020
    November 2020
    July 2020
    June 2020
    May 2020
    April 2020
    March 2020
    February 2020
    January 2020
    December 2019
    September 2019
    August 2019
    May 2019
    April 2019
    March 2019
    July 2018

About Us
Meet the board
Read our history
See our supporters
Learn More
Frequently asked questions
Special Assessment District
View documents
See updates
Get Involved
Donate
Attend a meeting
Contact us
Subscribe for email updates

Ask a question • Get our emails
©2025 | Four Lakes Task Force is a US 501 (c)(3) public charity, EIN 27-4698447. This institution is an equal opportunity provider.
Four Lakes Task Force
  • About
    • History
    • Who We Are >
      • Team Bios
    • Operations
    • Secord Dam
    • Smallwood Dam
    • Edenville Dam
    • Sanford Dam
  • Restoration Progress
    • 2025 Restoration Report
    • 2024 Restoration Progress Report
  • Environmental Restoration
    • Lakebottom Information
    • Restoration Projects
    • Erosion Control >
      • Project Permitting
      • What You Can Do
  • Donate
    • Why Donate?
    • Our Donors >
      • Corporate Sponsors
      • Individual Donors
    • Four Lakes Legacy Society
  • Events
  • Documents
    • Annual & Quarterly Reports
    • Audited Financials & Tax Filings
    • Dam Construction Updates
    • Engineering Reports & Studies
    • Flyers & Brochures
    • Meeting Presentations
    • News Flashes & Newsletters
  • Resources
    • FOIA Request
    • Frequently Asked Questions
    • Subscribe
    • Updates
  • Special Assessment District
    • Assessment Maps
    • FAQs
    • Prepayments
  • Contact