This paper summarizes the market conditions and major factors driving the price increase across each of the Four Lakes projects.
In July we placed concrete and achieved 95% installation completion of the Secord steel sheet pile auxiliary spillway among other things. These activities are closely monitored by the project team to ensure a durable final product.
Download/view the July construction udpates Our functional project team has built incredible programs related to the sections contained in this update, including the update itself. The communities we are working in and the authorities with jurisdiction over the projects have been second to none. The flow of permit issuance and modifications has been smooth and is key to maintaining progress. Our consultants have offered creative solutions to every challenge we've faced. And our contractor is a true partner.
Download/view the June construction updates August has been a very busy month, after the focus in July on obtaining the counties’ approval on the 2022-2024 Operations and Maintenance Special assessment. I wanted to provide a brief update of our progress and plans for the remainder of the year...
Read Full Report Restoration Plan Update: Status and Financing Plan (Chapters 10 and 11)
See original Restoration Plan published in May 2021 During the summer of 2021, Central Michigan University researchers surveyed for native freshwater mussels. These are the results:
|